Home |  News |  Conferences |  Commodities |  Publications |  Business Directory |  Resources |  Help
Go to the MEI Online homepage

click to find out about Process Mineralogy '18

 
Search Site:

MEI Online: Commodities: Metallic Ores: Gold: Latest News: February 5th 2008

 
 

click to find out about MEI Conferences

  

:: First Ore Processed at Etruscan’s Youga Gold Mine in Burkina Faso

Etruscan Resources Inc. (EET.TSX) reported today that the first ore has been fed to the processing plant at its Youga Gold Mine located in Burkina Faso, West Africa. The first gold pour is expected to occur later in February. Etruscan expects to achieve commercial production at Youga in March or April with the facility targeted to produce between 60,000 to 70,000 ounces of gold in calendar 2008.

The majority of the components of the Youga Gold Plant have now been fully tested with the last major phase of the testing being the recent successful startup of the grinding mill. The Youga Gold Plant has been commissioned in phases with each circuit going through a dry, a wet and lastly an ore based commissioning process. Commissioning began in late November with the startup of the crushing and screening circuit. This was followed by water testing of the CIL tanks and then the testing of the various mechanical equipment in December. In January final commissioning of the grinding mill and cyclone circuit commenced. The final recovery circuits (elution, gravity and goldroom) are ready to be operated and commissioned as the ore is treated. Some commissioning of the plant will continue into February as the equipment is properly adjusted and optimized.

Bob Harris, Vice President Operations of Etruscan Resources Inc. stated: “We are extremely pleased with how the commissioning phase has progressed at Youga. We are confident that the extra time we have taken during this phase will ensure that the plant reaches a steady state of production in the coming weeks and ramps up smoothly to full production in the coming months. A great deal of credit goes to our excellent operating team at Youga who have worked tirelessly over the past months to bring the Youga Gold Mine into production."

The mining activity has advanced with over 2.1 million tonnes blasted and 1.8 million tonnes excavated from the A2 Main pit. Grade control drilling has advanced with the first ore blocks blasted. Mining and stockpiling of the ore on the ROM pad is continuing.

The Youga Gold Project will initially be comprised of open pit mining from five pits with the ore being processed though a conventional CIL/gravity plant having a design capacity of one million tonnes per annum. Mineable reserves are 6.6 million tonnes with an average grade of 2.7 grams per tonne containing 580,000 ounces of gold. The project will benefit from a year-round water supply from a nearby major river system (the White Volta), and access to grid power supplied via the northern grid of the Volta River Authority in Ghana which is forecast for mid-2008. A full back-up power plant has been installed to ensure constant power to the site. The plant has been designed for maximum operating availability and in particular, the mill drive system was supplied new with a second new drive train (motor and gearbox) being stocked on site as a spare.

 

 

   

Click for more info on Comminution '18

Select the list(s) you'd like to join below, enter your email address, choose a content format and click "Join."
[more info]


MEI Online Update
MEI Online Job Vacancies

HTML Text

© 1998-2017, Minerals Engineering International


Email: amanda@min-eng.com