:: The Perfect Upgrade at Two Rivers

 

The construction of a new tertiary milling plant at the Steelpoort-based Two Rivers PGM mine is progressing rapidly and is set to come on stream towards the middle of this year. It will offer significant value in terms of additional PGM recovery, making it an attractive project, writes Laura Cornish. “The tertiary milling plant’s (TMP’s) sole purpose will be to retreat secondary rougher tailings to recover PGM material not recovered from the initial Two Rivers metallurgical process plant," explains Ken Dyamond, projects director at EPC project company Basil Read Matomo.

Having completed a project feasibility study at the beginning of last year, Basil Read Matomo was awarded the turnkey contract in March 2012 to design, build and commission the 250 000 tpm TMP, which remains on schedule to be completed and commissioned mid-2013.

The Two Rivers mine is a joint venture between African Rainbow Minerals (55%) and Impala Platinum (45%). It is situated on the farm Dwarsrivier on the southern part of the Eastern Limb of the Bushveld Igneous Complex. The mine delivers, on average, about 149 000 ozpa of platinum. “The plant will reprocess current arisings from the primary process plant, which will then be pumped via a tailings line through a tertiary milling circuit and flotation circuit, finally being returned to the main plant for further upgrade," explains Erik Bruggink, MD at Basil Read Matomo.

African Rainbow Minerals’ business development manager, Stompie Shiels says the project’s primary function is PGM enhancement. “It will remove chrome and we expect a 1% recovery improvement overall," he adds.

Despite having encountered one or two minor challenges on site, the impact on the project’s timeline has not altered. “We hit more under-surface rock than expected and as a result had to make various high adjustments to the terraces and to the foundations for the mill," Dyamond continues. “Because of the flat Basil Read Matomo management structure, and our general ‘can do’ attitude, challenges are quickly addressed and overcome, and in this particular case, with the hard work of the team under project manager Mark Wagner, we should bring the plant in ahead of the contractual completion date."

To date, the majority of the civil works has been completed, with the installation of all major mechanical equipment having commenced in January this year. The majority of the major equipment is on site, which will facilitate a smooth erection process.

The peak construction phase will start in the second quarter of this year, with about 160 people on-site. Located adjacent to the main plant, the TMP has been designed on a small, compact footprint and has been optimised in terms of power consumption, requiring only 3 MW to run at nameplate capacity.

The plant is designed to last between 20 and 30 years at its current size, which will not cater for future expansions. “It is designed for a specific purpose and will deliver on precise specifications. At Basil Read Matomo we offer throughput guarantees, meaning our clients are assured their plants will deliver according to their exact needs provided the plants have the specified feed."

Basil Read Matomo is well on its way to achieving its targeted Level 4 BEE status in the second quarter of 2013. “Contributions to local community upliftment and enterprise development have become key to our business going forward. In terms of enterprise development, we are ready to provide funding to a small local community project for the construction of an embankment," Dyamond notes.

Basil Read Matomo has been supporting a secondary school based in an informal settlement in Daveyton for a number of years, including the equipping of a library. Other CSI projects include the supply of solar flood lighting in the Eastern Cape with a second future project for lighting in the Steelpoort area to be undertaken later this year.

“Our enterprise development programme was resurrected at the end of 2012 in the Eastern Cape where a number of small HDSA owned businesses (some of which are 100% women owned) have been identified which operate in the construction or engineering consulting business in the Port Elizabeth area." These businesses have been supplied with various equipment which ranged from a vehicle to computer equipment and software packages and will be followed up with mentoring and coaching in an effort to make these up and coming businesses sustainable.

 

 

   

Click for more info on Comminution '18

Select the list(s) you'd like to join below, enter your email address, choose a content format and click "Join."
[more info]


MEI Online Update
MEI Online Job Vacancies

HTML Text

© 1998-2017, Minerals Engineering International


Email: amanda@min-eng.com