:: Commencement of Ore Processing at Kwale

 

Base Resources Limited is pleased to announce the commencement of ore processing through the mining unit and wet concentrator at the Kwale Project in Kenya.

Following two weeks of water commissioning and control logic testing, the first ore from the central dune has now been taken through the dozer trap mining unit and the wet concentrator. Over the next several weeks mining and processing rates are planned to be ramped up and a stockpile of concentrate built up ahead of the commissioning of the mineral separation plant (“MSP”).

Construction work on the MSP is now in its final stages with commissioning of the ilmenite and rutile circuits and commencement of concentrate processing expected during November. This will be followed by the zircon circuit in December. While some small container shipments are planned during December, the bulk shipments of finished product are now scheduled to commence in January.

The majority of the supporting infrastructure is now complete, with the access road, 132kv power supply, tailings storage facility and Mukurumudzi dam now functionally complete. The Likoni marine facility is scheduled for completion in November, well ahead of the first bulk shipment.

 

 

   

Select the list(s) you'd like to join below, enter your email address, choose a content format and click "Join."
[more info]


MEI Online Update
MEI Online Job Vacancies

HTML Text

© 1998-2017, Minerals Engineering International


Email: amanda@min-eng.com