:: Endeavour Mining Reports Delivery of Mining Equipment at Agbaou Gold Mine
Endeavour Mining Corporation announces that construction of its Agbaou Gold Mine in Côte d'Ivoire remains on-track for initial production in Q1 2014, with significant advances in completing the milling circuit and the recent arrival of mining equipment.
Agbaou Gold Mine Construction Highlights:
- To date, approximately 83% of the US$160 million construction budget has been committed, with US$103 million spent and the project is approximately 81% physically complete
- Ball mill and SAG mill installation is progressing well and should be completed by mid-August. Gearboxes and SAG and Ball Mill motors have been installed
- All civil works in the processing plant and mine services areas have been completed
- Electrical infrastructure for the 15km 91kV overhead power line is on target; tower installation and sub-stations are advancing well
- The Cyclone Cluster, Gravity Concentrator, and Mill lubrication systems have all been installed
- All administration buildings have been completed along with the Reagents storage sheds, Heavy Vehicle and Maintenance Workshop sheds
- The remaining structural steel has arrived on-site and is being erected, including for the gold room and conveyors
- Mining equipment, including D9 bulldozers, has arrived on site, with additional deliveries expected shortly; preparations for mining commencement are in line with key milestone dates
| |
|

|